JOHANNESBURG WATER: BRYANSTON A (Bryanston Drive, Grosvenor Drive, Cambridge Road)

Project Value:
Approximately: R 15,000,000.00

Project Description:
The Project Bryanston A involved the pipe replacement programme of approximately 12000 meters of pipelines in the above mentioned areas. Existing AC pipes were decommissioned and remain in the ground, old valves and fire hydrants were returned to the Depot. Steel pipe house connections were replaced by HDPE pipes from the main up to the water meters. Additional construction was requested in October 2009 in Bryanston Drive for a 160mm pipeline from William Nicol Road to Eaton Avenue and a 250mm diameter road crossing, including the change–overs from Cottesmore Road to Eaton Avenue

Programme:
29 September 2008 (site handover) – 9 November 2010 (Completion of Works)
7 December 2010 (Completion of Additional Works)

Services provided by DEC:
Project Management / Civil Engineering Consultants

PM Objectives:
DEC successfully met the proposed Scopes of work achieving and encompassing the Clients’ overall objectives of:

  • Utilising a team of qualified and skilled professionals such as DEC whose capacity allowed for the successful and timorous completion of the project.

DEC has successfully delivered its Civil Engineering Mandate in line with the proposed Scopes of work by implementing a high caliber of service and work ethic for Johannesburg Water.